The Xiaoyi City, Shanxi Province, Beijing Tianhai Zhi 100MW Energy Storage Frequency Regulation Power Station Project utilizes a combination of 50MW/50MWh lithium iron phosphate energy storage + 50MW/8MWh flywheel energy storage, with a planned land area of approximately 50 acres and a total investment of around 470 million RMB.
A 220kV boosting substation will be constructed along with a 100MW energy storage system planned to be connected to the 35kV side of the substation via five 35kV energy storage feeder lines. The project is scheduled to be grid-connected and operational by August 2025, participating in grid peak shaving and frequency regulation ancillary services.